FACTORYTALK SCHEDULER USER’S GUIDE
14
• • • • •
The BizBikes manufacturing resources
The BizBikes manufacturing plant contains seven work cells (Cut, Machine, Bend, Weld,
Finish, two Subassembly areas, and two Assembly and Pack areas), and a three-person
labor pool per shift (labor required by Subassembly and Assembly and Pack). All work
cells and labor are available for two eight-hour shifts, five days a week (a 2/5 composite
shift pattern). The first shift starts at 7
AM and ends at 3 PM. The second shift starts at 3 PM
and ends at 11
PM. There are no scheduled breaks in either shift. The key differences for
the processes at the various work cells are summarized below. Keep in mind that all setup
and process durations are expressed in hours.
Order # Product Name
Order
Quantity Release Date Due Date
SSD Red Finished Frame 2 SSD Red Finished Frame 24 2/12/03 11 PM 2/13/03 11 PM
SSD Red Finished Frame 3 SSD Red Finished Frame 24 2/18/03 11
PM
2/19/03 11
PM
SSD Blue Finished Frame 1 SSD Red Finished Frame 24 2/11/03 11 PM 2/12/03 11 PM
SSD Blue Finished Frame 2 SSD Blue Finished Frame 24 2/13/03 11 PM 2/14/03 11 PM
SSD Blue Finished Frame 3 SSD Blue Finished Frame 24 2/17/03 11 PM 2/18/03 11 PM
SSD Blue Finished Frame 4 SSD Blue Finished Frame 24 2/18/03 11 PM 2/18/03 11 PM
Handlebar Assembly 1 Handlebar Assembly 75 2/10/03 11 PM 2/11/03 11 PM
Handlebar Assembly 2 Handlebar Assembly 75 2/12/03 11 PM 2/13/03 11 PM
Handlebar Assembly 3 Handlebar Assembly 75 2/14/03 11 PM 2/17/03 11 PM
Handlebar Assembly 4 Handlebar Assembly 75 2/17/03 11 PM 2/18/03 11 PM
Handlebar Assembly 5 Handlebar Assembly 75 2/19/03 11 PM 2/20/03 11 PM
Seat Assembly 1 Seat Assembly 75 2/10/03 11 PM 2/11/03 11 PM
Seat Assembly 2 Seat Assembly 75 2/12/03 11 PM 2/13/03 11 PM
Seat Assembly 3 Seat Assembly 75 2/14/03 11 PM 2/17/03 11 PM
Seat Assembly 4 Seat Assembly 75 2/17/03 11
PM
2/18/03 11
PM
Seat Assembly 5 Seat Assembly 75 2/19/03 11 PM 2/20/03 11 PM
Handlebar 1 Handlebar 100 2/11/03 11 PM 2/14/03 11 PM
Handlebar 2 Handlebar 100 2/12/03 11
PM
2/17/03 11
PM
Handlebar 3 Handlebar 100 2/14/03 11
PM
2/19/03 11
PM
Neck Post 1 Neck Post 60 2/11/03 11 PM 2/14/03 11 PM
Neck Post 2 Neck Post 120 2/12/03 11 PM 2/17/03 11 PM
Neck Post 3 Neck Post 60 2/14/03 11
PM
2/19/03 11
PM
SHP Frame 1 SHP Frame 50 2/10/03 11 PM 2/14/03 11 PM
SHP Frame 2 SHP Frame 50 2/11/03 11 PM 2/17/03 11 PM
SSD Frame 1 SSD Frame 50 2/11/03 11 PM 2/17/03 11 PM
SSD Frame 2 SSD Frame 50 2/12/03 11
PM
2/18/03 11
PM
Seat Post 1 Seat Post 100 2/12/03 11 PM 2/17/03 11 PM
Seat Post 2 Seat Post 100 2/14/03 11 PM 2/19/03 11 PM
Commenti su questo manuale